The Memorial Arena roof repair project is getting close to the next phase of cutting the beams and installing new foundations.

City of Cranbrook staff said the assembly of the scaffolding being
used to hold up the roof structure is nearly done.

An official date to start up the ice plant and begin installing the ice sheet at the Kinsmen Arena has yet to be worked out.

Below are the current schedule highlights which are subject to change.

- Advertisement -

• January 10, 2024 – BC Hydro Disconnect
• January 12, 2024 – scaffold completion
• January 15, 2024 – begin cutting beams and excavation.
• January 17, 2024 – begin pouring concrete.
• January 29, 2024 – begin installing structural steel

City staff said the project is still on schedule with an early spring reopening.