Structural steel deliveries for the Dr. F.W. Green Memorial Home replacement project in Cranbrook will begin Tuesday as construction continues on the new long-term care facility.
The City of Cranbrook said deliveries will begin Sept. 8, with steel installation continuing through Dec. 15.
Temporary lane closures will affect portions of 18th Avenue South during that period to accommodate deliveries, steel installation and crane operations.

Offsite infrastructure work and temporary road closures, originally scheduled from July 22 to Sept. 1, have been extended to Oct. 12.
The extension is due to “unforeseen circumstances encountered during construction,” the city said.
Residents and the public may continue to experience temporary road closures and traffic disruptions in the surrounding area.
Noise-generating work, including machinery operation, will only take place during permitted work hours and will follow local bylaws.
The city said the contractor will contact residents whose properties front directly onto the work site to discuss access and answer questions.