The City of Fernie has submitted a formal response to the province following a provincial inspection of Fernie’s wastewater system and a compliance inspection report.
The compliance inspection report was issued for repeated instances where the City’s wastewater infrastructure was unable to manage inflows during peak conditions.
In an incident in December 2025, more than 24,000 cubic metres of untreated influent and stormwater were released into the river system over a number of days.
The report said sampling found elevated levels of E. coli and fecal coliforms in the environment.
No penalties were assigned in the report, but it is being referred for administrative penalty related to the City’s wastewater permit.
The city has now responded and said they have outlined actions underway to address the inspection findings.
Some of those measures include bringing the system up to compliance.
The city has invested approximately $860,000 over the past three years in environmental studies, system monitoring, and engineering design.
City officials said they are also in the process of procuring improved flow monitoring equipment.
“Protecting public health and the environment remains the City’s top priority. Extreme rainfall and atmospheric river events, linked to climate change, have increased pressure on wastewater systems across the province, including in Fernie,” he said.
“During these events, the City takes reasonable and necessary measures to minimize environmental impacts and protect critical infrastructure, while maintaining transparent and timely communication with provincial regulators and the public.”
More information on the city’s response can be found here.
Be the first to know! Don’t miss out on breaking news and daily updates in your area. Sign up to MyEastKootenayNow News Alerts.