Progress has been made in pre-construction activities for the Kimberley Wastewater Treatment Plant, a $90-million project slated to open in 2028.
Kimberley city council provided an update this week, noting that early onsite work — including road upgrades, excavation, clearing and the development of temporary work areas — was completed in late 2025. This work has prepared the site for construction to begin in spring 2026.
Mayor Don McCormick said the city is on track to begin building in April.
“All of the groundwork around where the facility is going to be built was finished late November so it’s all ready for early April. As soon as frost is out of the ground we will be able to get the back hose in the ground, so we are ready to rock ‘n’ roll with the construction of the facility. We fully expect we’re gonna be going first thing in April”. said McCormick.
Detailed design is underway and expected to finish by the end of Quarter 1 2026, along with BC Hydro installation planned for the same timeframe.
The City submitted a Municipal Wastewater Regulation (MWR) and early construction application for approval in September 2025 but had delays to the review due to a strike. Approval will be needed by January 2026 to avoid delaying construction and further costs as the hold up has already cost the city $250,000.
The project has received approval to switch to Aerobic Granular Sludge (AGS) technology.
The federal and provincial governments will update the Shared Cost Agreement in early 2026.
City officials said they remain committed to regular public communication and thanked staff, elected officials and residents for their continued support.
Ongoing collaboration with local First Nations is a priority, and the project team remains available to provide updates and support.
The next steps in place are to finish detailing the design of the project, complete BC Hydro electrical work and obtain MWR registration or early construction approval.


